Inspection visit

Fire Safety inspection

BRIA OF GENEVACMS #14606711 citations on this visit
11 citations recorded

Citations

11 citations recorded*CMS

This is a Fire Safety survey. CMS cites these findings under the Life Safety Code and Emergency Preparedness rules, a separate set from the health (F-tag) deficiencies. The codes and grading differ, so these do not link to the health violation pages.

What do CMS severity letters mean?

Serious (G-L). Actual harm to a resident, or immediate jeopardy. Codes G through I indicate actual harm; J through L indicate immediate jeopardy to resident health or safety.

General (A-F). No actual harm found, or harm that is minimal. The facility must still submit a Plan of Correction. Most CMS citations land here.

Each letter combines severity with scope: how many residents the deficiency affected.

  • 0222GeneralS&S Epotential for harm

    Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements.

  • 0291GeneralS&S Epotential for harm

    Install emergency lighting that can last at least 1 1/2 hours.

  • 0293GeneralS&S Fpotential for harm

    Have properly located and lighted "Exit" signs.

  • 0321GeneralS&S Epotential for harm

    Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.

  • 0324GeneralS&S Epotential for harm

    Provide properly protected cooking facilities.

  • 0345GeneralS&S Fpotential for harm

    Have approved installation, maintenance and testing program for fire alarm systems.

  • 0353GeneralS&S Fpotential for harm

    Inspect, test, and maintain automatic sprinkler systems.

  • 0363GeneralS&S Epotential for harm

    Install corridor and hallway doors that block smoke.

  • 0712GeneralS&S Fpotential for harm

    Have simulated fire drills held at unexpected times.

  • 0918GeneralS&S Fpotential for harm

    Have generator or other power source capable of supplying service within 10 seconds.

  • 0923GeneralS&S Epotential for harm

    Have proper medical gas storage and administration areas.

FAQ · About this visit

Common questions about this visit

What happened during the May 26, 2023 survey of BRIA OF GENEVA?

This was a inspection survey of BRIA OF GENEVA on May 26, 2023. The surveyor cited 11 deficiencies, recorded on the federal Form 2567 statement of deficiencies.

Were any deficiencies cited at BRIA OF GENEVA on May 26, 2023?

Yes, 11 deficiencies were cited, each with a CMS Scope and Severity grade. The first was: "Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arra..."

What type of survey was this?

This was a inspection survey conducted by state surveyors under federal Centers for Medicare & Medicaid Services (CMS) oversight. Findings are published on CMS Care Compare.

Share this reportEmail

Next steps

Concerned about a resident’s care?Find your local ombudsman through the Eldercare Locatoror file a complaint with your state survey agency.

Researching this visit professionally?Book a 15-minute calland we will walk through what we have on file.

Data from CMS Care Compare public records. Dataset last refreshed . If you believe any information is inaccurate, report it here.