Inspection visit

Fire Safety inspection

TORREY PINES POST ACUTE AND REHABILITATIONCMS #29504515 citations on this visit
15 citations recorded

Citations

15 citations recorded*CMS

This is a Fire Safety survey. CMS cites these findings under the Life Safety Code and Emergency Preparedness rules, a separate set from the health (F-tag) deficiencies. The codes and grading differ, so these do not link to the health violation pages.

What do CMS severity letters mean?

Serious (G-L). Actual harm to a resident, or immediate jeopardy. Codes G through I indicate actual harm; J through L indicate immediate jeopardy to resident health or safety.

General (A-F). No actual harm found, or harm that is minimal. The facility must still submit a Plan of Correction. Most CMS citations land here.

Each letter combines severity with scope: how many residents the deficiency affected.

  • 0029GeneralS&S Epotential for harm

    Develop a communication plan.

  • 0036GeneralS&S Epotential for harm

    Establish emergency prep training and testing.

  • 0037GeneralS&S Epotential for harm

    Establish staff and initial training requirements.

  • 0041GeneralS&S Dpotential for harm

    Implement emergency and standby power systems.

  • 0222GeneralS&S Epotential for harm

    Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements.

  • 0223GeneralS&S Dpotential for harm

    Provide exit doors that are held open by devices that will automatically close on the activation of a fire alarm or smoke detector.

  • 0006GeneralS&S Epotential for harm

    Conduct risk assessment and an All-Hazards approach.

  • 0013GeneralS&S Epotential for harm

    Develop Emergency Preparedness policies and procedures.

  • 0341GeneralS&S Dpotential for harm

    Install a fire alarm system that can be heard throughout the facility.

  • 0345GeneralS&S Epotential for harm

    Have approved installation, maintenance and testing program for fire alarm systems.

  • 0353GeneralS&S Epotential for harm

    Inspect, test, and maintain automatic sprinkler systems.

  • 0511GeneralS&S Dpotential for harm

    Have properly installed electrical wiring and gas equipment.

  • 0741GeneralS&S Dpotential for harm

    Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed.

  • 0918GeneralS&S Dpotential for harm

    Have generator or other power source capable of supplying service within 10 seconds.

  • 0926GeneralS&S Dpotential for harm

    Ensure that personnel concerned with handling of medical gases and cylinders are trained on the risk.

FAQ · About this visit

Common questions about this visit

What happened during the June 29, 2023 survey of TORREY PINES POST ACUTE AND REHABILITATION?

This was a inspection survey of TORREY PINES POST ACUTE AND REHABILITATION on June 29, 2023. The surveyor cited 15 deficiencies, recorded on the federal Form 2567 statement of deficiencies.

Were any deficiencies cited at TORREY PINES POST ACUTE AND REHABILITATION on June 29, 2023?

Yes, 15 deficiencies were cited, each with a CMS Scope and Severity grade. The first was: "Develop a communication plan."

What type of survey was this?

This was a inspection survey conducted by state surveyors under federal Centers for Medicare & Medicaid Services (CMS) oversight. Findings are published on CMS Care Compare.

Share this reportEmail

Next steps

Concerned about a resident’s care?Find your local ombudsman through the Eldercare Locatoror file a complaint with your state survey agency.

Researching this visit professionally?Book a 15-minute calland we will walk through what we have on file.

Data from CMS Care Compare public records. Dataset last refreshed . If you believe any information is inaccurate, report it here.