Citations
13 citations recorded*CMS
This is a Fire Safety survey. CMS cites these findings under the Life Safety Code and Emergency Preparedness rules, a separate set from the health (F-tag) deficiencies. The codes and grading differ, so these do not link to the health violation pages.
What do CMS severity letters mean?
Serious (G-L). Actual harm to a resident, or immediate jeopardy. Codes G through I indicate actual harm; J through L indicate immediate jeopardy to resident health or safety.
General (A-F). No actual harm found, or harm that is minimal. The facility must still submit a Plan of Correction. Most CMS citations land here.
Each letter combines severity with scope: how many residents the deficiency affected.
- 0007GeneralS&S Cno actual harm
Address patient/client population and determine types of services needed.
- 0026GeneralS&S Cno actual harm
Establish roles under a Waiver declared by secretary.
- 0252GeneralS&S Epotential for harm
Provide at least two remote exits on each floor or fire section of the building.
- 0293GeneralS&S Dpotential for harm
Have properly located and lighted "Exit" signs.
- 0321GeneralS&S Epotential for harm
Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.
- 0345GeneralS&S Epotential for harm
Have approved installation, maintenance and testing program for fire alarm systems.
- 0353GeneralS&S Dpotential for harm
Inspect, test, and maintain automatic sprinkler systems.
- 0355GeneralS&S Dpotential for harm
Properly select, install, inspect, or maintain portable fire extinguishes.
- 0761GeneralS&S Epotential for harm
To conduct inspection, testing and maintenance of fire doors by qualified individuals.
- 0901GeneralS&S Epotential for harm
Ensure that building systems meet requirements determined by risk assessment procedures performed by qualified personnel.
- 0921GeneralS&S Epotential for harm
Ensure that testing and maintenance of electrical equipment is performed.
- 0923GeneralS&S Dpotential for harm
Have proper medical gas storage and administration areas.
- 0363GeneralS&S Epotential for harm
Install corridor and hallway doors that block smoke.
FAQ · About this visit
Common questions about this visit
What happened during the June 4, 2024 survey of TOLSTOY FOUNDATION REHABILITATION AND NRSG CENTER?
This was a inspection survey of TOLSTOY FOUNDATION REHABILITATION AND NRSG CENTER on June 4, 2024. The surveyor cited 13 deficiencies, recorded on the federal Form 2567 statement of deficiencies.
Were any deficiencies cited at TOLSTOY FOUNDATION REHABILITATION AND NRSG CENTER on June 4, 2024?
Yes, 13 deficiencies were cited, each with a CMS Scope and Severity grade. The first was: "Address patient/client population and determine types of services needed."
What type of survey was this?
This was a inspection survey conducted by state surveyors under federal Centers for Medicare & Medicaid Services (CMS) oversight. Findings are published on CMS Care Compare.
SourceView on CMS Care Compare
Next steps
Concerned about a resident’s care?Find your local ombudsman through the Eldercare Locatoror file a complaint with your state survey agency.
Researching this visit professionally?Book a 15-minute calland we will walk through what we have on file.
Data from CMS Care Compare public records. Dataset last refreshed . If you believe any information is inaccurate, report it here.